Sunday 25 August 2013

Construction Journey - Clarendon Waterfall 37+3 (RA)


Stage 1 - Site Acceptance & Excavation - 5 June 2013


- Builder accepted the site and put up steel fence. 
- Ground excavated

Stage 2 - Slab Stage - 12 to 15 June 2013

- Piering completed
- Foam work completed
- Concrete Poured



Stage 3 - Frame Stage - 29 June 2013




Stage 4 - First Storey Brickwork - 10 July



Stage 5 - Brickwork 95% completed -16 July)



Stage 6 - Roof completed - 27 July


Stage 7 - Eves completed - 16 Aug 


Stage 8 - Scaffolding lowered + Down pipes - 23 Aug