Construction Journey - Clarendon Waterfall 37+3 (RA)
Stage 1 - Site Acceptance & Excavation - 5 June 2013
- Builder accepted the site and put up steel fence.
- Ground excavated
Stage 2 - Slab Stage - 12 to 15 June 2013
- Piering completed
- Foam work completed
- Concrete Poured
Stage 3 - Frame Stage - 29 June 2013
Stage 4 - First Storey Brickwork - 10 July
Stage 5 - Brickwork 95% completed -16 July)
Stage 6 - Roof completed - 27 July
Stage 7 - Eves completed - 16 Aug
Stage 8 - Scaffolding lowered + Down pipes - 23 Aug